datacentergrid.dev

On-site gas

Twenty20 Frame 5 Order

Canonical Summary

Baker Hughes will supply Twenty20 Energy 10 Frame 5 turbines, up to 250 MW, for Georgia and Texas data centers.

Lead Organization
Baker Hughes
Key Technical Metric
Up to 250 MW
Maturity / Status
Deliveries in 2027
Governance / License
Frame 5 turbine award

Technical Specifications

Announced 11 February 2026
Equipment 10 Frame 5 gas turbines and associated generators
Capacity Up to 250 MW
Sites Twenty20 Energy data center projects in Georgia and Texas
Deliveries Initial deliveries scheduled for 2027
Broader deal Parties are moving toward a multi-gigawatt supply agreement
Verification: reported · Retrieved: 2026-10-19 · Primary Source Reference